[Netarchivesuite-devel] NetarchiveSuite: Desired task for next iteration (39)

Christen Hedegaard chh at kb.dk
Thu Oct 1 11:09:11 CEST 2009


Dear all,

As the release test for iteration 38 is in progress please also have a look on the next tasks to be defined in iteration 39.
http://netarchive.dk/suite/Iteration39TaskList

Please note that iteration 39 will be a stable release. Estimated to be ready in start of November 2009.
Implementation phase is estimated to be completed Friday October the 23rd to ensure sufficient time for the stable release test.

Kåre will as QA for NetachiveSuite create a prioritized list of bugs and Feature requests for iteration 39.
So will Claus as Daily Manager of Netarkivet.dk.

But it's also important for BNF and ONB to prioritize bugs and features to be implemented in iteration 39.

Please insert the prioritized task in the list of task for iteration 39
http://netarchive.dk/suite/Iteration39TaskList
with the following priority options (next stable release is iteration 39)

 *   Priority 4 : Must be fixed in next stable release.
 *   Priority 3 : Should be fixed in next stable release. (Default value)

Sara and Nicolas: As BNF has a hard deadline for the stable release (November 2009) please make sure the bugs and/or FR that must be included in iteration 39 is listed as priority 4.

Eleonora and Andreas: As you have started production harvest using the NetarchiveSuite package it's of course important to ensure that major inconveniences realized in your production environment have been fixed or will be fixed in iteration 39.

Estimated timetable.
1. The release test of iteration 38 is estimated to be completed tomorrow Friday October the 2nd.
2. The stop of code freeze is estimated to be on Monday October the 5th
3. Start of iteration 39 implementation phase is estimated to be Monday October the 5th
4. End of implementation phase for iteration 39 is estimated to be Friday October the 23rd.

Please send an email to the devel mailing list if it's not possible to complete your iteration task(s) within the estimated implementation phase for iteration 39.


Best regards

Christen


-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.gforge.statsbiblioteket.dk/pipermail/netarchivesuite-devel/attachments/20091001/3a8874db/attachment.html 


More information about the Netarchivesuite-devel mailing list